बुंदेलखंड पैकेज (एक परिचय)

Bundelkhand at a Glance

Number of Districts
-
7

No. of Blocks
-
47

Total no. of Revenue Villages
-
5374

Total no. of Gram Panchayats  
-
2669

Total Population ( 2001 Census)
-
61.61 Lakh

SC/ST Population
-
20.71 Laks (33.61%)

Total Population of BPL
-
19.47 Lakh (31.60%)

Total no. of Micro-watersheds in the Bundelkhand Region.
-
4172 (Ares 29.42 Lakh Ha.)

Total No. of treatable Micro-watershed in Bundelkhand Region.
-
3414 (Area 24.22 Lakh Ha.)

Pre IWMP Micro Watershed Covered in Bundelkhand Region
-
2157 (Area 15.67 Lakh Ha.)

Micro Watershed covered under IWMP during 2009-10
-

217 (Area 1.70 Lakh Ha.)
(Treatable area = 1.35 Lakh Ha.)

Proposed Micro Watershed coveredUnder IWMP during 2010-11
-
438 (Area 3.52 Lakh Ha.)
(Treatable area = 2.70 Lakh Ha.)

Micro Watershed yet to be covered in Bundelkhand Region
-
602 (Area 3.33 Lakh Ha.)

बुंदेलखंड पैकेज से आच्छादित जनपद

District Covered Under Bundelkhand Package

Jhansi
Lalitpur
Jalaun
Hameerpur
Mahoba
Banda
Chitrakoot

Command Area Development & Water Management Programme (CAD & WM)

काडम की भौतिक प्रगति (बुंदेलखंड)

S.NO.

Item

Unit

Target

Ach.

%

1

Survey

000 ha.

42.00

42.00

100

2

Planning

000 ha.

42.00

42.00

100

3

Area covered

000 ha.

48.84

11.37

23

4

Kacchi gul

Km.

3157

336.61

11

5

Packki gul

Km.

714

94.49

13

6

WC Structures

No.

2100

560

27



काडम की वित्तीय प्रगति (बुंदेलखंड)


Financial  Target

--

Rs. 126.00 Cr.

Funds released to PIAs

--

Rs. 125.00 Cr.

Expenditure upto 31-3-2011

--

Rs. 40.84 Cr.

Expenditure during 15th Nov. 2011

--

Rs. 4.58 Cr.

Expenditure upto 15th Nov. 2011

--

Rs. 28.68 Cr.

Cumulative Expenditure upto 15th Nov. 2011

--

Rs. 69.52 Cr.

Percentage

--

56%



काडम की वित्तीय कार्य योजना (बुंदेलखंड)

राशि करोड़ में

2011-12 के लिए महीना वार लक्ष्य

वार्षिक लक्ष्य

अक्टूबर 2011 तक खर्च

नवम्बर 2011 

दिसम्बर  2011

जनवरी  2012

फ़रवरी 2012

मार्च 2012

योग

84.00

26.93

14.00

14.00

14.00

15.07

--

57.07